江津在线婷婷 发表于 2019-6-28 18:12:59

江津日报:轨道5号线江津段4个车站主体基本完工,即将进入装修

6月27日,记者从区轨道办获悉,备受市民关注的轨道交通5号线跳磴至江津段又有新进展,正在建设的双福、享堂、江津高铁、圣泉寺4个车站主体工程已基本完工,接下来将进入装修阶段。

http://m.e47.cn/source/plugin/csdn123_news/display_picture.php?url=https%3A%2F%2Fmmbiz.qpic.cn%2Fmmbiz_jpg%2FD9qzfX4UzdB3nTpaG5y5wDovZsKEfiaJrsDxqJiaRj1GTib6RyDH1qicNYJ1mtHHlW0XhtVpNibXuUXunicaPibukSnQg%2F640%3Fwx_fmt%3Djpeg
按照目前的建设进度,轨道5号线江津境内土建主体工程预计2019年内实现全面完工,并启动江津境内的铺轨工作,预计在建段2020年底建成投入试运行。

当前进度
目前,轨道交通5号线跳磴至江津段江津区内桩基、墩柱已经全部完成,箱梁完成97%,南北大道各路基段完成结构施工,明挖隧道开挖完成1510米,暗挖隧道完成开挖贯通,车辆段开挖土石方已基本完成,生产用房全面进入基础施工阶段;中梁山隧道掘进3890米。
http://m.e47.cn/source/plugin/csdn123_news/display_picture.php?url=https%3A%2F%2Fmmbiz.qpic.cn%2Fmmbiz_jpg%2FD9qzfX4UzdB3nTpaG5y5wDovZsKEfiaJrEVPHrtZeyrLFfxg6qfEKsn2lvZzGibYSTZibFOSq52bZ8yhCRDiaV3sqw%2F640%3Fwx_fmt%3Djpeghttp://m.e47.cn/source/plugin/csdn123_news/display_picture.php?url=https%3A%2F%2Fmmbiz.qpic.cn%2Fmmbiz_jpg%2FD9qzfX4UzdB3nTpaG5y5wDovZsKEfiaJrGESjvZh7K9F3EQG0Vdh8xT1xWDVlW00AEknBMcLibNOFNaRzCTzOA3Q%2F640%3Fwx_fmt%3Djpeghttp://m.e47.cn/source/plugin/csdn123_news/display_picture.php?url=https%3A%2F%2Fmmbiz.qpic.cn%2Fmmbiz_jpg%2FD9qzfX4UzdB3nTpaG5y5wDovZsKEfiaJrIXZvtJBvOqwJXqEDvVvMssTzKlthflMgoQ6Kp5TreGELFMOt5Qze9g%2F640%3Fwx_fmt%3Djpeghttp://m.e47.cn/source/plugin/csdn123_news/display_picture.php?url=https%3A%2F%2Fmmbiz.qpic.cn%2Fmmbiz_jpg%2FD9qzfX4UzdB3nTpaG5y5wDovZsKEfiaJrvvos32kpza8Ej566BH5vLa3wX5xTFzJzbNdEZuskJZmDdPwIxtzyVw%2F640%3Fwx_fmt%3Djpeghttp://m.e47.cn/source/plugin/csdn123_news/display_picture.php?url=https%3A%2F%2Fmmbiz.qpic.cn%2Fmmbiz_jpg%2FD9qzfX4UzdB3nTpaG5y5wDovZsKEfiaJrQESW8zlrj5vr4BrviaicS96hw6Q2qPOVuSswE82GcOMeaXarfoeWECug%2F640%3Fwx_fmt%3Djpeghttp://m.e47.cn/source/plugin/csdn123_news/display_picture.php?url=https%3A%2F%2Fmmbiz.qpic.cn%2Fmmbiz_jpg%2FD9qzfX4UzdB3nTpaG5y5wDovZsKEfiaJrebXuu19yictoSCpcJ8HI4VTENhHPgicbibpcx5Wjm4X3VPLFOVptniberA%2F640%3Fwx_fmt%3Djpeg
无需换乘直达重庆主城
作为市政府确定的100个重点关注项目之一,轨道交通5号线跳磴至江津段起于轨道交通5号线跳磴站,途经华福路、九江大道、南北大道,止于滨江新城,全长28.22公里。
http://m.e47.cn/source/plugin/csdn123_news/display_picture.php?url=https%3A%2F%2Fmmbiz.qpic.cn%2Fmmbiz_jpg%2FD9qzfX4UzdB3nTpaG5y5wDovZsKEfiaJreH457HQ5d7LqeHflqF6Eric7UJDSCP97JpGslZFN2IRdjvGqMmUFzFg%2F640%3Fwx_fmt%3Djpeghttp://m.e47.cn/source/plugin/csdn123_news/display_picture.php?url=https%3A%2F%2Fmmbiz.qpic.cn%2Fmmbiz_jpg%2FD9qzfX4UzdB3nTpaG5y5wDovZsKEfiaJrLPjs3rHMnP33WrsNlA3mQm5Y5cgvaafyFPrlqYaxjYvNPT0OmEELSQ%2F640%3Fwx_fmt%3Djpeghttp://m.e47.cn/source/plugin/csdn123_news/display_picture.php?url=https%3A%2F%2Fmmbiz.qpic.cn%2Fmmbiz_jpg%2FD9qzfX4UzdB3nTpaG5y5wDovZsKEfiaJribvsHt96hAQn7ibI8ZQm6WFaqqkvKmdDBH4fKNSD7mORvND1O4ILNjAA%2F640%3Fwx_fmt%3Djpeghttp://m.e47.cn/source/plugin/csdn123_news/display_picture.php?url=https%3A%2F%2Fmmbiz.qpic.cn%2Fmmbiz_jpg%2FD9qzfX4UzdB3nTpaG5y5wDovZsKEfiaJraBaqqyEwQnkwibJdRP8ib3U0SKmxx3hSjRKicMfJz61pqv20nQAPkyssQ%2F640%3Fwx_fmt%3Djpeghttp://m.e47.cn/source/plugin/csdn123_news/display_picture.php?url=https%3A%2F%2Fmmbiz.qpic.cn%2Fmmbiz_jpg%2FD9qzfX4UzdB3nTpaG5y5wDovZsKEfiaJrwJoVSjrXG29kfNr6wmVIme5ia5PHbr07NoV7GUxA2xL77wsWd1py5Pg%2F640%3Fwx_fmt%3Djpeg
http://m.e47.cn/source/plugin/csdn123_news/display_picture.php?url=https%3A%2F%2Fmmbiz.qpic.cn%2Fmmbiz_jpg%2FD9qzfX4UzdB3nTpaG5y5wDovZsKEfiaJrrwYgBV5S4w0EMjxwtClAy6Bx97zjTq1puT1rI1CiaRNwB5vXEDSuFmw%2F640%3Fwx_fmt%3Djpeg
http://m.e47.cn/source/plugin/csdn123_news/display_picture.php?url=https%3A%2F%2Fmmbiz.qpic.cn%2Fmmbiz_jpg%2FD9qzfX4UzdB3nTpaG5y5wDovZsKEfiaJrbDQu6Tuk8YJnvsZyFSSV42lKPuWnDVmyH7x46hSTo9O0Zic4SjgosZA%2F640%3Fwx_fmt%3Djpeg

其中地下线长5.8公里,高架线及地面线22.42公里。江津区15.8公里,占全程的56%;主城区12.42公里,占全程的44%。建成后与主城轨道交通5号线贯通,市民无需换乘即可直达重庆主城。
期 待!
来源:江津日报

允我心安 发表于 2019-6-28 18:35:33

一会19年底短通轨,一会19年底开始铺轨,2020年通车,敢不敢有个准信!
自媒体能不能不要吹!

津城勇哥哥 发表于 2019-6-28 18:59:52

允我心安 发表于 2019-6-28 18:35
一会19年底短通轨,一会19年底开始铺轨,2020年通车,敢不敢有个准信!
自媒体能不能不要吹!
...

兄弟 看清楚 这篇报道的出处 是 江津日报

小白l 发表于 2019-6-28 19:51:37

这个新闻就是夏天说着凉快,冬天说起来热乎

幽浮上帝之手 发表于 2019-6-29 09:52:49

好消息传来,江津在建的轨道交通5号线跳蹬至江津段,4个车站主体工程已基本完工,离建成通车时间又快了一步!

metoo564 发表于 2019-6-29 09:52:59

江津段和大渡口段一点也不担心,最让人牵挂的是九龙坡段

贼帅的小乐 发表于 2019-6-29 09:53:07

江津人民希望轻轨5号线早日建成通车。

爱吗想吗念么 发表于 2019-6-29 09:53:20

这个工程修了好多好多年了,滨江新城占道施工很严重,早点修通才是硬道理,不要吹了吧,2O2O年能修通吗?

赤兔粉丝团团长 发表于 2019-6-29 09:53:49

看了“一条巨龙”延伸到江津的报道,我心里多少有点高兴、这条“巨龙”从开始计划到开工修建已经有点年份了,今年终于看见了工程将在明年完工并且年底将开通直通主城,作为江津人我为家乡点赞,愿家乡越来越好!

蓝调和风 发表于 2019-6-29 09:53:58

半小时进主城!指日可待呀!